A Preinstallation Checklist for Electric Roof Access Skylights on US Projects
An electric roof access skylight does two jobs on a flat or low-slope roof: it brings daylight into the space below, and it opens wide enough for a person to step out onto the roof. Flat-roof penthouses are a common application, where one unit provides both daylight and terrace access. Because the unit is motorized and glazed overhead, much of the work that makes installation smooth happens before delivery. This checklist is for architects, general contractors, project managers and engineers planning one into a US project.
Start with the opening and the stair below
The skylight’s clear opening has to line up with the stair or ship ladder that reaches it from below. On a retrofit such as a brownstone, existing joists rarely land where you want them. A structural engineer should confirm which members can be cut or headed off. Check headroom the same way. Trace the full swing or slide of the sash against bulkheads, parapets, planters and anything else on the roof.
Request the opening and curb drawings from the manufacturer during schematic design. A curb is the raised frame, usually built on site, that the unit sits on above the roof membrane. Those drawings fix the structural opening, the curb dimensions, the anchorage points and the finished flashing height. Every other trade works from them.
Confirm loads, glazing and thermal performance
The roof structure has to carry the unit’s dead load plus regional loads. Those range from snow in northern states to wind uplift on coastal sites. Your structural engineer needs the unit weight and anchorage requirements early enough to size the framing. In wind-borne debris regions, impact-resistant glazing may be required, so confirm that with the authority having jurisdiction before any glass is ordered.
Overhead glazing is commonly required to use a safety build-up, often laminated glass on the inner pane. The project glazing specification identifies the required build-up for each opening.
Energy codes set separate targets for U-factor, the rate of heat loss through the assembly, and for solar heat gain. Solar heat gain coefficient, usually shortened to SHGC, measures how much of the sun’s heat passes through the glass.
Record the project-specific whole-unit U-factor and SHGC targets in the same specification package. Putting both values in one place helps glazing selection match the energy model.
A thermally broken frame has an insulating element inside the aluminum profile. It slows heat transfer and can reduce condensation risk in humid interiors. Once the configuration is selected, review the manufacturer’s documentation for the chosen unit, such as the Sunsquare USA electric roof access skylight page, and request the project-specific load, glazing, thermal and wiring data at the start of design.
Plan the electrical rough-in before the roof closes
The actuators, the motorized arms that lift the sash, need power and control wiring run to the opening. Confirm the manufacturer’s wiring requirements with the electrical contractor during rough-in, while walls and ceilings are still open. The coordination list usually covers:
- Dedicated power to the opening, sized from the manufacturer’s documentation
- Control wiring, plus the location of wall switches, keypads, remotes or touch panels
- Integration with access control or a building automation system, if specified
- How the unit will be operated during a power outage
Electrical rough-in is often the coordination step that slips.
If wiring isn’t in place before the roof deck and finishes close, the fallback is surface conduit or reopened finishes. Both are difficult to hide in a finished interior. Confirm who supplies the control panel and who programs it, because that split varies by manufacturer.
Sort out delivery, lifting and roof access
Electric roof access units are large and heavy, and a crane or material hoist may be needed to get one to the roof. On urban retrofits, lifting can mean a street closure or a crane permit. Book it early and confirm the rigging plan against the supplier’s delivery documents. Walk the route from truck to roof and note overhead wires, trees, scaffolding and neighboring structures.
If a crane isn’t an option, measure the unit against the stair and bulkhead route before delivery day. Time the delivery to the roofing schedule.
Coordinate delivery with the curb installation and the manufacturer’s flashing sequence. With some curb-mounted systems, the curb is flashed and weathered in before the unit is set. If the unit has to wait on site, arrange weather protection and a level area that can bear the weight.
Close out with commissioning and handover
Once power is connected, run the unit through full open and close cycles and test every control location you specified. Photograph the wiring and the open unit before the ceilings close. Record the wiring routes and control positions on the as-built drawings so the facilities team isn’t tracing cables later.
Handover should include the manufacturer’s operating and maintenance instructions, warranty documents, glazing care guidance and the final control settings.
The checklist follows the sequence of the work, because each step fixes dimensions or services that the next trade depends on. Working through it before delivery gives the framer, the roofer, the electrician and the glazier the same information at the same time and reduces the chance that a heavy motorized unit will delay the schedule.